Flood Restoration Work at Lake Wa-Con-Da
Updated April 3, 2014
Completion of the Sand Berms with Soil Cover. Mark Hughes Construction of Glenwood, IA will be completing the sand berm installation along the levee east of East Lake Drive. Upon completion of the sand installation Mark Hughes Construction will be seeding the soil cover on the sand berms.
Work is schedule to begin in early April 2014 and be completed in May 2014.
East Lake Drive Road Restoration. Kerns Excavating Co. Inc. of Plattsmouth, NE will be regrading East Lake Drive from the Cobb Community Center to Bull Frog Bay with installation of storm sewer pipes and inlets to improve drainage. The project has been divided into four zones to limit the inconvenience to accessing private property during the construction. We will be posting weekly updates on this project once work is underway.
Work is scheduled to begin in mid-April 2014 and be completed by June 6, 2014.
West Shore Drive Road Restoration. Kerns Excavating Co. Inc. of Plattsmouth, NE will be regrading West Shore Drive from the Entrance to the Levee road. Excess surfacing material will be removed to improve drainage. This material will be utilized for surfacing the boat trailer storage area. We will be posting periodic updates on this project once work is underway.
Work is scheduled to begin in April 2014 and be completed by June 6, 2014.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home.
Work is scheduled to be completed in June 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on or before June 15, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed above.
Updated April 3, 2014
Completion of the Sand Berms with Soil Cover. Mark Hughes Construction of Glenwood, IA will be completing the sand berm installation along the levee east of East Lake Drive. Upon completion of the sand installation Mark Hughes Construction will be seeding the soil cover on the sand berms.
Work is schedule to begin in early April 2014 and be completed in May 2014.
East Lake Drive Road Restoration. Kerns Excavating Co. Inc. of Plattsmouth, NE will be regrading East Lake Drive from the Cobb Community Center to Bull Frog Bay with installation of storm sewer pipes and inlets to improve drainage. The project has been divided into four zones to limit the inconvenience to accessing private property during the construction. We will be posting weekly updates on this project once work is underway.
Work is scheduled to begin in mid-April 2014 and be completed by June 6, 2014.
West Shore Drive Road Restoration. Kerns Excavating Co. Inc. of Plattsmouth, NE will be regrading West Shore Drive from the Entrance to the Levee road. Excess surfacing material will be removed to improve drainage. This material will be utilized for surfacing the boat trailer storage area. We will be posting periodic updates on this project once work is underway.
Work is scheduled to begin in April 2014 and be completed by June 6, 2014.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home.
Work is scheduled to be completed in June 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on or before June 15, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed above.