Road Repair Project Update 6-20-2014
East Lake Drive. Kerns Excavating is working on grading the sand berm and placing topsoil. They will be focusing on fine grading and completing the installation of the storm sewer. After completion of the shoulder clean-up they will continue with placement of topsoil. They will generally be working in the area near the boat ramp access road but will be on all portions of the disturbed section of East Lake Drive. Rock surfacing will continue on the private drives disturbed during this project. The parking lot east of the playground has been enlarged southerly toward the Community Building allowing spaces for an additional 18 vehicles.
Following this work, asphalt millings and smaller rock will be placed on East Lake Drive and smoothed out in preparation of the Chip Seal project slated for July.
West Shore Drive. Clean up work will be completed on West Shore Drive and the remainder of the seeding and matting will be completed. Kerns Excavating will be working from the North to the South. Work is expected to be complete the week of June 23, 2014.
Bull Frog Bay Drive. Grading on Bull Frog Bay Drive is schedule to be completed the week of June 23, 2014 with the installation of the storm sewer and drainage swale adjacent to Lot 217.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home. Anticipated start date is to be July 21, 2014.
Work is scheduled to be completed in July 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on July 7, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed.
East Lake Drive. Kerns Excavating is working on grading the sand berm and placing topsoil. They will be focusing on fine grading and completing the installation of the storm sewer. After completion of the shoulder clean-up they will continue with placement of topsoil. They will generally be working in the area near the boat ramp access road but will be on all portions of the disturbed section of East Lake Drive. Rock surfacing will continue on the private drives disturbed during this project. The parking lot east of the playground has been enlarged southerly toward the Community Building allowing spaces for an additional 18 vehicles.
Following this work, asphalt millings and smaller rock will be placed on East Lake Drive and smoothed out in preparation of the Chip Seal project slated for July.
West Shore Drive. Clean up work will be completed on West Shore Drive and the remainder of the seeding and matting will be completed. Kerns Excavating will be working from the North to the South. Work is expected to be complete the week of June 23, 2014.
Bull Frog Bay Drive. Grading on Bull Frog Bay Drive is schedule to be completed the week of June 23, 2014 with the installation of the storm sewer and drainage swale adjacent to Lot 217.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home. Anticipated start date is to be July 21, 2014.
Work is scheduled to be completed in July 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on July 7, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed.