Road Repair Project Update 6-03-2014
East Lake Drive. Kerns Excavating will continue work on East Lake Drive. They will be focusing on fine grading and completing the installation of the storm sewer near the boat ramp access road. After completion of the shoulder clean-up they will began placement of topsoil. They will generally be working from the north to south but will be on all portions of the disturbed section of East Lake Drive.
Rock surfacing will continue on the private drives disturbed during this project. The parking lot east of the playground will be enlarged southerly toward the Community Building allowing spaces for an additional 18 vehicles.
Following this work, asphalt millings and smaller rock will be placed on East Lake Drive and smoothed out in preparation of the Chip Seal project slated for June and July.
Scheduled Water Shut off.
The water is scheduled to be shut off to the entire lake Thursday, June 5, at approximately 8:30 am until late-afternoon. It is necessary to shut the drinking water system off to perform maintenance on a couple of the valves and to install a hydrant. Please watch the SID Website & sign at entrance of lake for updates.
West Shore Drive. Construction on West Shore Drive will continue with material being removed to reestablish grade. Kerns Excavating will be working from the North to the South. Grading on Bull Frog Bay Drive is schedule to be completed by early June utilizing material removed from West Shore Drive.
Kerns’ work on East Lake Drive is scheduled to be completed by early June with work on West Shore Drive to be completed by mid-June.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home.
Work is scheduled to be completed in June 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on or before June 15, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed.
East Lake Drive. Kerns Excavating will continue work on East Lake Drive. They will be focusing on fine grading and completing the installation of the storm sewer near the boat ramp access road. After completion of the shoulder clean-up they will began placement of topsoil. They will generally be working from the north to south but will be on all portions of the disturbed section of East Lake Drive.
Rock surfacing will continue on the private drives disturbed during this project. The parking lot east of the playground will be enlarged southerly toward the Community Building allowing spaces for an additional 18 vehicles.
Following this work, asphalt millings and smaller rock will be placed on East Lake Drive and smoothed out in preparation of the Chip Seal project slated for June and July.
Scheduled Water Shut off.
The water is scheduled to be shut off to the entire lake Thursday, June 5, at approximately 8:30 am until late-afternoon. It is necessary to shut the drinking water system off to perform maintenance on a couple of the valves and to install a hydrant. Please watch the SID Website & sign at entrance of lake for updates.
West Shore Drive. Construction on West Shore Drive will continue with material being removed to reestablish grade. Kerns Excavating will be working from the North to the South. Grading on Bull Frog Bay Drive is schedule to be completed by early June utilizing material removed from West Shore Drive.
Kerns’ work on East Lake Drive is scheduled to be completed by early June with work on West Shore Drive to be completed by mid-June.
Asphalt Repair. Old Castle Materials Midwest Co. d/b/a/ Omni Engineering of Omaha, NE will be making repairs to the section of the asphalt road damaged during the flood fight and restoration efforts. This includes repair to the cuts through West Shore Drive near the Caretaker’s home.
Work is scheduled to be completed in June 2014.
Chip Seal. Sta-Built Construction of Harlan, IA will be stabilizing the road base on East Lake Drive, West Shore Drive and Bull Frog Bay Drive. Upon stabilization of the road base a seal coat surface will be applied to all roads including Mid Lake Drive. The seal coat surface incudes the application of asphaltic cement and loose rock. Some tracking of the loose stone is expected in this process.
Work is scheduled to be begin on or before June 15, 2014 and be completed by July 31, 2014.
No work is allowed on July 3, 2014 through July 6, 2014 and the road will be in a passable condition for passenger vehicles during the period of July 3 through July 6, 2014. Chip seal surfacing will not be applied until July 7, 2014. Weekend and night work is allowed with the exception of the days listed.